Notes
Slide Show
Outline
1
Reactor Economics 2008
  • Jim Harding
  • National Academy of Sciences/National Research Council Panel
  • January 22, 2008
  • Washington, DC
2
How Do Current Estimates Compare?  What Factors Are Most Important?
  • Capital cost is most important
    • EIA - $2083/kW
    • MIT - $2000-2500/kW (2003)
    • Keystone - $3600-4000/kW (June 2007)
    • S&P - $4000/kW (May 2007)
    • Moody’s - $5000-6000/kW (October 2007)
    • FP&L - $5200-7800/kW (Fall 2007)
  • Operating costs less important but not insignificant
  • Assumptions and methodology often opaque
  • Life cycle cost estimates range from 5-17 cents/kWh
  • Why is this so?



3
The Easy Reasons – for all resources
  • Lack of a consistent economic methodology
    • Capital cost usually stated in mixed current dollars at COD, rather than discounted real dollars
    • Subsidies often included in cost estimates, though they affect price not cost
    • Very important for long lead time, capital intensive units
  • Example:  Keystone high case for nuclear was $2950/kW overnight, $4650/kW mixed current dollars at COD, and $4000/kW in discounted 2007 dollars.
  • All the same number!
4
Nuclear Power is Tougher
  • Lack of recent North American nuclear construction experience
  • Historical reliance on “studies” and vendor software
    • Studies often reference each other
    • Software assumes Asian construction practices, and excludes owner’s costs – contingency, escalation, interest during construction, land, transmission, and oversight.  Long lead time for recalculating
    • Little incentive to be accurate or  up-to-date; no real money being spent
    • MIT chose actual Asian values, but assumed no real escalation
  • Long lead time; licensing, siting, rate recovery and financing uncertainties.  Very problematic in states with deregulated retail markets.
  • Escalation during construction not considered; first of a kind premiums and learning curves instead
  • Supply-chain imbalances not considered (skilled labor, sub-suppliers)
  • Transmission costs and lead time usually not considered
5
Recent Asian Experience
6
Major Keystone Assumptions
  • Take Asian experience at face value (important)
  • Escalate at EPRI estimate for heavy construction, 2002-2007 in low case and through COD in high case (very important)
  • 5-6 year construction period and no major finance or regulatory issues; conventional IOU financing (all very important)
  • Use current spot prices for uranium, and predicted enrichment prices for long term fuel prices (not very important)
  • O&M and capacity factor at current fleet average; include decommissioning, capital additions, and A&G; 30-40 year life (somewhat important)
  • Life cycle cash flows discounted at weighted after tax cost of capital (somewhat important; first year cost – “rate shock” - can be twice as high as levelized life cycle cost)
  • No major new transmission required (important, but site specific)
7
Real Escalation is the Biggest Problem
8
 
9
 
10
Escalation Likely Worse for Nuclear
  • Industry moribund in Western Europe, US, and Russia since TMI and Chernobyl
  • Twenty years ago (US):  400 suppliers, 900 N-Stamp holders; today 80 and 200
  • Only one forge for large parts – Japan Steel Works; maybe Creusot Forge (France)
  • Skilled labor and contractor limits
  • World uranium production well below current consumption
11
Recent Estimates
  • Keystone - $3600-4000/kW; 8-11 cents/kWh
    • Discounted real 2007 dollars; would be $5600/kW (16-17 cents/kWh) at AEP escalation rate from 2002-COD
  • Standard & Poor’s - $4000/kW; 9-10 cents/kWh
    • Basis not stated; levelized fixed charge rate
    • Life cycle costs reflect Keystone O&M and fuel costs
  • Moody’s - $5000-6000/kW
    • Basis not stated; operating and fuel costs not estimated
  • Florida Power & Light - $5200-7800/kW
    • Basis not stated; major transmission included
12
 
13
Life Cycle and Operating Costs Also Vary
  • Nuclear O&M costs estimates often do not include
    • A&G costs
    • Net capital additions
    • Decommissioning
  • Nuclear fuel cost estimates often do not include
    • Current spot prices for uranium
    • Likely increase in enrichment prices
  • Life cycle cost estimates often use simplified levelized fixed charge rates rather than more complex discounted cash flows


14
 
15
US Projections – Decades Ago
16
 
17
 
18
 
19
 
20
 
21
Supplemental Slides
22
Efficiency and Renewables Can Be  Disruptive Technologies
  • A disruptive technology is often cheaper than the operating cost of the existing system
  • Demand is not limited to growth in service
  • Efficiency resources cost less than operating costs for existing gas (or coal with carbon taxes); they pay for themselves with +3x more carbon savings per dollar
  • Wind was disruptive from 2002-2005 and may be again
  • Photovoltaics may soon become one
  • Only disruptive energy technologies can grow fast enough to solve climate challenges
23
 
24
Technical Innovation Driven by Standards
25
 
26
 
27
 
28
The Bottom Line
  • Twenty years from light water reactor technology will be roughly the same as it is today
  • Efficiency resources, wind turbine technology, and photovoltaics are improving rapidly
  • Take one example --- Nanosolar
    • started by the Google founders, backed also by Swiss Re
    • Building two 430 MW/yr thin film PV production facilities this year in Germany and California, using a technology they equate to printing newspapers
    • Currently shipping and reportedly profitable at $0.99/watt (not including installation and balance of system)
  • The cheapest, least risk strategy is rapid development of efficiency resources